Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the Park Projects topic
No spam. Unsubscribe anytime.
Parks director breaks down Dante building estimate; commissioners seek hard bids
Summary
Staff laid out a line-item construction cost estimate for the Dante Fa—ade community building that put the shell at about $634 per square foot and the total building budget near $3.57 million; commissioners asked for bid-level detail and options to reduce scope.
Get email alerts on the Park Projects topic
No spam. Unsubscribe anytime.
Parks staff presented a line-by-line construction estimate for the Dante Facade community building during the July 29 workshop that raised questions about scope and unit costs.
The parks director said the building component was estimated at about $2.3 million and that a shell construction rate of about $634 per square foot had been used in the estimate. The director identified site preparation ($179,000), civil utility work ($231,000), interior electrical (~$400,000), and plumbing/mechanical (~$489,000) among the line items that contribute to the building total.
Commissioners pressed staff to confirm which costs are design fees versus construction scope and requested hard bids and a more detailed cost breakout to evaluate scope-reduction options. Several commissioners said a $3.8 million budget for roughly 3,600 square feet appears high and asked staff to return with procurement-ready figures and alternatives to bring the per‑square‑foot cost down.
