Board OKs up to $4,100 for sidewalk replacement at 302 N. Maple; one trustee abstains
Summary
Trustees approved spending up to $4,100 to replace sidewalk at 302 N. Maple Street after receiving a higher estimate because of increased concrete costs; Trustee Caleb Grover abstained.
Get email alerts on the Sidewalk Repair topic
No spam. Unsubscribe anytime.
A bid from Quality Construction & Concrete for sidewalk replacement at 302 N. Maple Street was presented. The contractor's original bid of $3,096.00 was updated to $4,100.00 due to higher concrete costs, and the board was asked to authorize the increased amount.
Trustee Tara Ramsey moved to authorize up to $4,100.00; Trustee Scott Kuntzman seconded. The motion passed 5-0 with Trustee Caleb Grover recorded as abstaining. President Dowdy noted the cost increase reflected market conditions for concrete.
Minutes do not record a scheduled start date or contractor contract details; the board directed staff to proceed with the authorization.