Board approves $23,600 to build developer entrance road while TIF eligibility is checked
Summary
To enable site access for a proposed TIF-area development, trustees approved a $23,600 expenditure to construct a 200-foot entrance road pending confirmation of TIF eligibility; members agreed the expense could be reimbursed or credited if the project qualifies for TIF funds.
Get email alerts on the Economic Development topic
No spam. Unsubscribe anytime.
Trustees voted to authorize roughly $23,600 to build an entrance road to a development parcel to provide immediate access while staff confirms whether the work can be paid from TIF funds. The board discussed the trade-off between waiting for TIF approval and constructing a base road now so the developer and site work can progress; staff advised the board it would revisit funding if the work proves TIF-eligible.
A village representative described the recommended technique (core out and recycled asphalt base) and the estimated cost. "We're looking at the project cost that you got with $23,600 to get the road 200 foot back in there like we asked before," a staff member said. Trustees approved moving forward with the entrance road funding and asked staff to confirm TIF eligibility with Moran before additional TIF-dependent work begins.