Board awards Bartlett Cocke CMAR role and preconstruction fee for Elementary #9
Summary
Liberty Hill ISD named Bartlett Cocke as Construction Manager at Risk for Elementary #9 and approved a $56,250 preconstruction services fee funded by the 2023 Bond program; the board voted 6-0 to authorize negotiation of final contract terms.
Get email alerts on the Construction Elementary 9 topic
No spam. Unsubscribe anytime.
The board approved awarding Bartlett Cocke as the Construction Manager At Risk for Liberty Hill Elementary #9 and authorized a preconstruction services fee of $56,250 funded by the 2023 Bond program. The motion was made by Kristi Hargrove and seconded by Brandon Canady; the vote was unanimous (6-0). The board authorized the interim superintendent or designee to negotiate final contract terms.
The minutes record the fee and funding source but do not include the scope schedule or guaranteed maximum price; those details will be determined during preconstruction negotiations and returned to the board as appropriate.