Clifton approves grant application for Newton Falls sewer upgrades; grinder pumps ordered
Summary
The board authorized submission of a Fall 2025 Northern Border Regional Commission grant application for WWTP Disinfection & Improvements (Resolution No. 9-2025, vote 4–0) and minutes note that Newton Falls Sewer District ordered two small grinder pumps and one larger pump.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
The Town of Clifton board approved Resolution No. 9-2025 authorizing submission of a Fall 2025 Northern Border Regional Commission grant application for the Newton Falls Sewer District WWTP Disinfection & Improvements Project. The vote was unanimous: Blackmer = Y, Griffin = Y, Zuhlsdorf = Y, Russell = Y.
The minutes also record that the Newton Falls Sewer District has ordered grinder pumps—two small pumps and one large pump—to support system operations. The resolution authorizes pursuing external funding for disinfection and improvements at the wastewater treatment plant; the minutes do not include the requested grant amount or the timeline for grant submission.