Board approves contract for MHS practice gym after schematic shows $627,000 under-budget estimate

Midway Independent School District Board of Trustees · March 24, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Huckabee, Inc. presented a schematic for a 23,000-square-foot MHS practice gym; the Board approved by consent a contract with Mazanec Construction and authorized the superintendent to execute the contract.

Aubrey Moses of Huckabee, Inc. presented the schematic design for the Midway High School athletics addition on March 24, describing a new 23,000-square-foot practice gym, new locker rooms, coaching and meeting spaces, and a mezzanine for cheer practice.

Moses told trustees the project is currently estimated to be $627,000 under budget at this design stage. The Board approved, on the consent agenda, a contract with Mazanec Construction for the MHS gym and locker room addition and delegated authority to the superintendent to execute the contract on behalf of the Board.

The contract approval was bundled into consent agenda item 10A and carried with unanimous support in that vote (For: Jordan Barry, Jonathan Green, Rick Tullis, Susan Vick, Pam Watts, Colin Witt; Absent: Brad Alford). The schematic presentation and the contract authorization together move the project into procurement and execution phases pending standard contract administration steps.