Board approves $7.15 million guaranteed maximum price for high school baseball facility
Summary
The Marble Falls ISD Board approved a Guaranteed Maximum Price of $7,152,778 with American Constructors for the Marble Falls High School Baseball Facility under the 2025 Bond Program. The vote was unanimous.
Get email alerts on the Bond Projects topic
No spam. Unsubscribe anytime.
The Marble Falls Independent School District Board approved a Guaranteed Maximum Price (GMP) of $7,152,778 with American Constructors for a new Marble Falls High School baseball facility at its March 23 meeting.
Superintendent Dr. Jeff Gasaway presented the project scope, expense breakdown and timeline, and the board approved the GMP after a motion by Gary Boshears and a second by Larry Berkman. The motion carried with six votes in favor and none against; one board member, Mandy McCary, was absent.
The presentation described design details and a project schedule delivered under the district's Construction Manager at Risk arrangement. No amendments to the GMP were recorded in the meeting minutes; the district will proceed with final scheduling and contractor coordination under the 2025 Bond Program.