Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Facilities topic

No spam. Unsubscribe anytime.

Superintendent outlines construction timeline, roof work and athletic-field progress

Board of Trustees, Munday Consolidated Independent School District (Munday CISD) · October 23, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Superintendent Mike Parton reported construction progress and roof recommendations, including a projected Dec. 1 completion for baseball and softball dugouts, a recommended full roof teardown per TASB guidance, and an approximate work schedule/costing option noted in the meeting record.

Superintendent Mike Parton told the board on Oct. 23 that district construction and improvements are underway and provided a schedule and cost context. He reported roughly 90 weekday work days remaining, discussed a $500-per-day option and a credit of about $6,000–$7,000 for certain work, and said TASB (cited via David Booe) recommended a total teardown of the roof with leftover bond funds to be used toward a down payment.

Parton also said mortar and other work on the baseball and softball facilities are progressing, dugouts are about to begin construction, and a Dec. 1 completion date was targeted in the meeting record. The transcript contains these figures and projected dates but did not include full contract terms or final budgets.