Drainage Authority approves $166,046.41 in payments and a $13,800 change order for Krueger Excavating
Summary
The Faribault County Drainage Authority on July 7 unanimously approved multiple payments to Krueger Excavating of Albert Lea, LLC — including invoices and pay applications totaling $166,046.41 — and authorized a $13,800 change order for added ASIs on the JCD23FM repair.
Get email alerts on the Drainage Projects topic
No spam. Unsubscribe anytime.
The Faribault County Drainage Authority unanimously approved multiple payments and a change order on July 7, 2026, to Krueger Excavating of Albert Lea, LLC, covering several ditch and repair projects. Actions approved included an invoice batch, final payout and retainage for CD72, pay application #2 for CD73, and a change order plus pay application #2 for the JCD23FM repair.
Approved amounts included an invoices package for $73,524.06; final pay and retainage for the CD72 tree removal project for $13,967.81; pay application #2 for the CD73 Open Ditch repair for $25,887.50; and a $54,171 pay application for JCD23FM repair. The board also authorized change order #2 for JCD23FM totaling $13,800 to add seven ASIs. All motions carried unanimously.
The motions were recorded in the meeting minutes with the following movers and seconders: Groskreutz/Young for the invoices approval, Young/Groskreutz for the CD72 final payment, Loveall/Paschke for the CD73 pay application and the JCD23FM items, and the voting was recorded as carried unanimously. The approvals authorize the county to disburse the listed amounts to the contractor and to proceed with the added ASI work on JCD23FM.
The approvals reference Krueger Excavating of Albert Lea, LLC as the contractor paid for these projects. The Drainage Authority recessed to July 21, 2026, after completing the listed business.