Council reviews resurfacing toolbox: cape-seal pilot, PCI metrics and DeWitt rebuild plans
Summary
Public works staff reviewed the city’s street resurfacing program, Powell Bill funding, a cape-seal pilot (1.6 miles, ~$250,000) and plans to bid a challenging DeWitt Street project; staff emphasized selective use of cape-seal and upcoming pavement-condition assessment for FY27 prioritization.
Get email alerts on the Pavement Management topic
No spam. Unsubscribe anytime.
Public services staff provided an overview of Jacksonville’s resurfacing program, explaining Powell Bill distribution and the city's approximate FY allocation (just under $2.2 million). The city maintains about 166.5 miles of streets and uses a toolbox of treatments informed by pavement condition indices (PCI); staff reported an average PCI of about 58 from a 2023 assessment.
Staff presented results from a cape‑seal pilot (1.6 miles, ~$250,000) and cost comparisons: mill-and-overlay near $500,000/mile, cape‑seal about $150,000/mile, and full reconstruction estimates cited at roughly $3.5 million/mile. Speaker 11 said cape‑seal can be a cost‑effective preventive tool on appropriate segments but is not suitable for structurally failed streets like DeWitt, where deeper sewer and subgrade issues require reconstruction; DeWitt permitting is underway with bids planned once permits are complete. Council discussed funding options (renewed consideration of a 0.25¢ sales-tax for roads, EV fees, and pursuing grants) and staff plans to issue an RFQ for an updated pavement-condition program to better schedule crack-seal, cape-seal, and mill-and-overlay work.
Next steps: staff will pursue the FY27 assessment and propose a prioritized resurfacing list and possible budget amendments; staff also said they would continue selective use of cape-seal where effective and prepare the DeWitt project for bid.