Superintendent Matt told the council the town's water-main replacement project is proceeding on schedule, with a tie-in between Washington and Broadway planned for Wednesday; lead-and-copper tests showed no exceedances.
Get email alerts on the Infrastructure Water topic
No spam. Unsubscribe anytime.
Superintendent Matt told the Town Council the water-main replacement project is on schedule and crews plan a tie-in on the alley between Washington and Broadway on Wednesday. He also reported that the town's lead-and-copper testing "came back with no exceedances."
The report said crews will continue work on services, then move on to Marie and finally Gobblers Knob. Mayor DeVere used the reports to highlight that regional water and sewer agreements will require renegotiation as nearby systems are interdependent; he asked that legal, staff and committee input be included in future interlocal agreement discussions. The council did not take immediate action on the project at the meeting.