Pumping station project delayed; Council asks for USDA proof on $80,430 inspection amendment
Summary
GMB told the council the pumping station project missed its Nov. 29 substantial completion date and may finish in January 2026. GMB requested an amendment to add full-time inspection services (maximum $80,430) as required by USDA; the Council tabled the amendment pending documentation from USDA.
Get email alerts on the Pumping Station Project topic
No spam. Unsubscribe anytime.
Representatives from engineering firm GMB, Jason Lytle and Andrew Lynch, updated the Trappe Town Council on the Pumping Station project and said the work is behind schedule. The project had been scheduled for substantial completion on Nov. 29, 2025, with 30 additional days to final completion, but GMB reported the schedule is slipping and completion is now expected in January 2026.
GMB presented an amendment to the owner–engineer agreement to provide additional full‑time inspection services that, they said, are required by the U.S. Department of Agriculture (USDA). The amendment was presented as a maximum of $80,430; the amendment would be adjusted downward as services are used. Council members requested written documentation from USDA confirming that full‑time inspection is required and tabled action on the amendment until the December meeting.
No vote on the amendment was taken at the Nov. 5 meeting; Council directed staff to obtain USDA documentation before taking formal action.