Aerial video shows admin/media building nearing completion; classroom building pushed about a month
Summary
Parish McCall's Chris Shepherd showed an aerial flyover of the campus work: admin/media foundation and CMU walls close to complete, hollow-core plank and truss shipments scheduled this summer; cafeteria and classroom work lags the admin/media building by roughly a month and temporary fencing/walkways are in place for school opening.
Get email alerts on the Site Logistics topic
No spam. Unsubscribe anytime.
Chris Shepherd of Parish McCall presented an aerial video and described the site layout and schedule. He said the admin/media building foundation and CMU walls were nearly complete and listed near-term milestones (truss/deck and hollow-core plank dates). Shepherd noted the classroom building was delayed by about a month relative to admin/media and that temporary pedestrian routes, scaffolding protection and fencing were installed for student safety.
Shepherd reviewed allowances and pay-app accounting for the campus program, noting several allowances were carried for unknown items (including a $1,250,000 generator allowance) and that allowances and ODPs will be reconciled as buyout proceeds. Committee members asked for site plans and building-number maps; Shepherd said he would email the documents to district staff.