County delays ERP go‑live to Jan. 1, adds roughly $20,000
Summary
County finance director reported a slip in the ERP implementation that pushes the financial module live from Oct. 1 to Jan. 1 and estimated a roughly $20,000 budget impact tied to extra vendor sessions and staffing time.
Get email alerts on the Finance Erp topic
No spam. Unsubscribe anytime.
Kevin Gutierrez, the county finance director, told commissioners that interim audit work is complete but that the county’s ERP (Tyler Tech) implementation slipped. "We were not going to be able to be successful with an October 1 go live for the financial module," Gutierrez said, and staff negotiated a three‑month delay so the system will now go live for most modules on January 1, with the asset management module to follow later.
Gutierrez estimated the schedule change will cost about $20,000 — funds that are currently covered in the project appropriation but that draw from contingency. He said the delay reflects workload and staffing constraints and that the county will align HR/payroll cutover with the calendar year to avoid tax and payroll accumulator issues. Commissioners asked for confirmation of the timeline and next steps; finance staff said they will prioritize resources to meet the new date.