Sugar Creek Park bridge substructure complete; steel truss fabrication to take 12–24 weeks
Summary
Officials reported the bridge substructure at Sugar Creek Park is finished and CDG Engineering has approved Pace Construction's drawings, allowing the fabricator to begin manufacturing steel trusses; staff estimated a 12–24 week fabrication timeline before installation can start.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
Commission staff reported progress on the Sugar Creek Park bridge. The substructure is complete and CDG Engineering has approved Pace Construction's steel-truss drawings, which permits the bridge fabricator to begin manufacturing components.
Staff cautioned that the specialized nature of the steel fabrication means production and delivery could take roughly 12–24 weeks from the start of manufacturing. Once the trusses are completed and shipped to Sugar Creek Park, Pace Construction can begin installation.