Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
Council approves pool consultant amendments; staff targets pool fill late August
Summary
Council unanimously approved amendments reallocating contingency funds for special inspections ($100,000) and additional architecture/construction support ($229,020). Project managers said both pools have been tiled and the team is targeting the last week of August to fill them, followed by a 6–8 week commissioning period for the all‑electric heating and controls.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
City staff presented two contract amendments tied to the Piedmont Community Pool project: a not‑to‑exceed $100,000 amendment with Griffin Structures for special inspections and testing and a not‑to‑exceed $229,020 amendment with ELS Architecture & Design to extend construction‑support services. Public Works Director Daniel Gonzalez and project manager John Hughes characterized the changes as reallocations within the approved project budget (moving funds from hard‑cost contingency to soft‑cost contingency) rather than requests to increase the overall appropriation.
John Hughes and the contractor explained special inspections are time‑and‑materials and that sequencing changes and unforeseen underground conditions had increased inspection needs. Architect Clarence Lemoyak described extended construction administration work and said his firm had deferred billing for months; the requested amendment would cover work through the anticipated finish. "Right now, that milestone is targeted for the last week of August. We expect to fill the pool the last week of August," the project team said, and cautioned the public that filling the pools triggers a multi‑week commissioning period (estimated six to eight weeks) to tune the innovative all‑electric heating and controls. Council moved and approved both amendments unanimously.
