Multiple public commenters urged the committee to delay the expansion, use existing funds to repair the current jail, press Oklahoma City for a larger share of operations, and warned a larger facility would increase incarceration and disproportionately impact marginalized communities.

Public comment at the Citizens Oversight Committee meeting was dominated by concerns about project scope, long-term cost and equity.

Mark Falk told the committee the project risks creating a larger jail that will be filled: "When you build a larger jail, you fill it, and that's a fact," he said, adding that a county estimate of about $76,000,000 per year could grow into "a tax that is $3,600,000,000 on the citizens of Oklahoma County" over 25 years if sales tax revenue grows. Falk urged repairing the existing facility first and reconsidering the need for new capacity.

Sean Cummings and Christopher Johnson echoed fiscal and management concerns. Cummings questioned why municipalities outside Oklahoma City would be asked to subsidize what he said would be a facility driven by Oklahoma City bookings; he also criticized past land purchases and projected interest costs. Johnson said a reported $24,000,000 surplus had not been spent on repairs such as elevators and argued operational issues—staffing, cleanliness and management—remain the priority over capital work.

Jennifer Mayo, identified as a resident, said voters entrusted $260 million in 2022 for jail work and that the current proposal appeared vague about what a new sales tax would cover; she also cited that 64% of bookings last year came from Oklahoma City and asked whether other cities would be asked to subsidize a facility that primarily serves Oklahoma City bookings. "Do not move forward with recommending this tax proposal," she said.

Committee members acknowledged the criticism and for some the public comments reinforced the need to add oversight, a lockbox and a cap on size and cost before recommending a ballot question.

The meeting did not reconcile the numeric claims made by commenters—committee members asked for additional financial oversight input and left final language and verification of figures to bond counsel and county staff.