District seeks one-foot easement quitclaim to enable hydrant lateral for Madam Creek project

Tall State Public Utility District Water Committee · September 11, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Staff asked the committee to approve a quitclaim of a one-foot sliver of a 17-foot sewer easement to clean up title on one parcel while obtaining a water easement to install a hydrant lateral between Fern and Cherry; staff said Division of Drinking Water approved a reduced separation for the alignment and that the remaining 16-foot easement will preserve the sewer.

Will Stelter, the district's engineering manager, described a proposed quitclaim that would remove a one-foot sliver from an existing 17-foot sewer easement so the district can record a new water easement to install a fire hydrant lateral between Fern and Cherry. "The existing sewer easement is 17 feet wide, and so this quick claim would be a 1 foot sliver," he said. Stelter explained the change removes an encumbrance on one parcel while leaving a 16-foot sewer easement across the other properties and that the relocation is intended to meet fire district spacing needs.

Stelter said the Division of Drinking Water granted approval to allow less than 10 feet separation between the water line and sewer line in this alignment, enabling both utilities to fit spatially in the corridor. He characterized the settlement with the property owner as "a win win all the way around," and recommended the committee place the item on the board consent agenda. The transcript records the staff presentation and questions but no public comment or formal vote.