District staff recommend $219,548 amendment for West Lake Tahoe treatment plant construction support

Tall State Public Utility District Water Committee · September 11, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

District engineering staff recommended approval of Amendment No. 6 to Kennedy Jenks' construction support contract for the West Lake Tahoe Regional Water Treatment Plant to cover extended commissioning and testing work; staff said the 2025 budget includes funds and the item was slated for the board's consent agenda.

Sara Houssang Johnson, the district's director of engineering, told the committee she was recommending approval of Amendment No. 6 to the professional services agreement with Kennedy Jenks for ongoing construction support work at the West Lake Tahoe Regional Water Treatment Plant. "The amendment amount is in is the amount of $219,548," she said, and explained the extra budget covers extended engineering services and facility start-up testing after the project’s construction schedule slipped.

Johnson said the previous amendment had anticipated a February 2025 completion date but additional commissioning and acceptance with the state Division of Drinking Water extended the work. She told directors the district has budgeted for the amendment in 2025 and proposed the item for the board's consent agenda. No public comment was taken on the item during the meeting. The committee did not record a roll-call vote in the transcript; staff presented it as a consent item to go to the full board.