Wayzata board recommends $535,000 award for West Middle School window rehabilitation
Summary
Board packet recommended awarding the West Middle School window rehabilitation contract to Northern Glass & Glazing for $535,000; project funded from Long-Term Facilities Maintenance revenue and recommended by ZMD Engineered Solutions.
Get email alerts on the Facilities topic
No spam. Unsubscribe anytime.
The Wayzata Public Schools board considered a recommendation to award the West Middle School window rehabilitation contract to Northern Glass & Glazing, Inc. for the base bid of $535,000. Administrators said the project includes removal of existing windows and installation of a new window system, funded from the district’s Long-Term Facilities Maintenance (LTFM) revenue.
ZMD Engineered Solutions, the district’s project reviewer, told the district in a formal recommendation that it had reviewed the bids and “it is our opinion that Northern Glass & Glazing, Inc. is capable of performing the Work as specified.” ZMD also noted Northern Glass & Glazing has satisfactorily completed similarly scoped work for other districts and facilities in the state.
The bid opening was held Feb. 25, 2025, and the administration presented the lowest responsible bidder and supporting tabulation as part of the consent agenda. The board packet included expected start and completion dates (start 6/9/2025; completion 8/22/2025) and unit-price line items used for evaluation. The project manager’s letter and the bid tabulation were provided to board members before the recommendation.
Next steps in the agenda packet called for formal award of the contract; the packet noted the project will be coordinated with district operations and that the awarded contractor confirmed it can complete the work for the submitted amount.