District outlines $72M Tahoe Cedars and $9M Madden Creek water reconstruction plans; no vote today
Summary
Staff briefed the board on a long-term funding and financing strategy for two major water-system reconstructions: Tahoe Cedars (current estimate $72,000,000) and Madden Creek phase 4 (estimated $9,000,000), described likely financing sources and timing, and said no board action was requested at this meeting.
Get email alerts on the Infrastructure Financing topic
No spam. Unsubscribe anytime.
Staff presented an informational update on the district’s long-term water-infrastructure financing strategy for two reconstruction projects.
The presentation identified the Tahoe Cedars reconstruction as the larger project, now estimated at $72,000,000 in current dollars, and Madden Creek phase 4 at about $9,000,000. Staff listed likely funding sources — the State Revolving Fund (SRF), federal WIFIA loans, USDA rural development loans, and potential congressional-directed (earmark) grants — and said staff would prioritize SRF funding where possible for lower interest rates.
"For Tahoe Cedars water system reconstruction project, it is, it is estimated at $72,000,000," staff said during the briefing. Project facts shared with the board included an anticipated roughly 15 miles of new public pipeline, an estimated ~100 new fire hydrants, and over 1,200 new service extensions and meters. Staff also showed that the district’s current long-term financial plan assumes an annual debt-service impact in the neighborhood of $3.9 million (30-year basis) under present assumptions.
No action was requested at the meeting; staff signaled they will return with specific financing documents and recommended next steps (JPA, reimbursement resolution, rating engagement) in the coming months.