Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
Council approves $8,776 contract modification to repair structural issues at Fair Store glass sidewalk
Summary
Bisbee approved Modification No. 1 with Marsh Development Inc. adding $8,776 to repair unreinforced CMU walls uncovered during rehabilitation of the Fair Store glass sidewalk at 37 Main Street, with costs covered by the project's roughly $20,000 grant contingency. The council endorsed the contractor's work and approved the modification unanimously.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
Public Works Director Matthew Gurney told the council that unforeseen structural deficiencies—unreinforced and ungrouted concrete masonry unit (CMU) walls—were discovered after removing sidewalk panels during the Fair Store glass sidewalk rehabilitation at 37 Main Street. Modification No. 1 would use rebar, grout and new center support walls to restore structural integrity.
Gurney said the $8,776 modification will be paid from the project's approximately $20,000 grant contingency fund rather than the city's operating budget. Councilmember Karen Schumacher praised the contractor Marsh Development Inc. for professionalism and communication. Council approved the modification unanimously.
