District unveils Deer Path cafeteria renovation and 10‑year health and life‑safety plan
Summary
District staff presented a Perkins and Will health and life‑safety survey and a 10‑year capital roadmap that includes a Deer Path cafeteria renovation (punch‑through windows, movable glass partition, restroom refresh) with heavy work scheduled to start June 9 and further storefront replacement planned for summer 2026.
Get email alerts on the Capital Improvements topic
No spam. Unsubscribe anytime.
District facilities staff presented a health and life‑safety (HLS) assessment produced with Perkins and Will and described a 10‑year capital improvements roadmap that prioritizes urgent (A), required (B) and recommended (C) work across district buildings. The HLS process is required every 10 years in Illinois and will inform roofing, HVAC, accessibility and plumbing plans.
"On the Deerpath cafeteria, which is actually gonna really kick off June 9 with the heavy work, but we're gonna start a little bit of work next week over spring break," Mr. Mortensen said, outlining the project's schedule and the district's plan to remove flooring and prepare the space for a concentrated summer construction window. He described specific scope elements that include punch‑through windows on the serving line, a movable glass partition to open the hub area into the cafeteria, refreshed multi‑user restrooms and potential kitchen equipment upgrades.
Mortensen emphasized accessibility work guided by ADA checklists and Illinois accessibility codes; the team also expects to replace an original single‑pane storefront facing the patio in a Phase C project slated for summer 2026. Staff said they will use the Deer Path work as a model for restroom and finish decisions across other schools, allowing the board to evaluate finishes before district‑wide rollouts.
Next steps include final reports and any required amendments from ISBE after review of the submitted HLS documentation; staff said they will present a finalized 10‑year capital improvement plan and life‑safety amendments to the board for future approval.