Kermit ISD board approves $1.85M pay application and accepts Walton Field as complete, releases $361,525 retainage

Board of Trustees Kermit ISD · April 15, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Kermit ISD Board on April 15 approved pay application #4 to A Brush Above Services for $1,854,569.39 and accepted final completion of Walton Field, authorizing release of retainage of $361,525.55; the votes were unanimous.

On April 15, 2026, the Kermit ISD Board of Trustees approved Pay Application #4 for A Brush Above Services (ABA) in the amount of $1,854,569.39, following presentations by Gallagher and Parkhill consultants and a recommendation from Superintendent Oscar Muniz.

The board later found the Walton Field project 100% complete and authorized final payment and release of contract retainage totaling $361,525.55 to ABA, LLC. Trustee Miguel Urquidi moved to accept final completion and authorize the superintendent to execute the Certificate of Final Completion; Vice‑President Ramiro Antillon seconded the motion. The approval and the retainage release were recorded as unanimous actions by the seven board members present.