Board signs multiple construction change orders and approves large bond invoices tied to Kermit ISD additions
Summary
Trustees approved a sequence of construction change requests for high school and elementary additions, accepted credits totaling more than $50,000 on one item, and approved bond-related invoices including Trane applications and a $1,066,854.45 application from A Brush Above Services, LLC.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
Kermit ISD trustees voted on multiple construction change requests (CCRs) related to the High School CTE addition and the Elementary School addition and approved bond-related invoices during the March 18 meeting. Parkhill Architects’ Ashlee Horsley and Gallagher and ABA representatives presented the changes. Approved CCRs included a $2,277 request for added Smart Board outlets, a $29,504.75 manufacturer-change cost for panic devices, a $52,834 credit for roofing buy-back, a $2,741 credit for interior finish changes, and additional change orders ranging from $2,026.53 to $10,821.38 for site and systems work.
The board also approved multiple invoices tied to the 2023 bond project by unanimous vote, including Trane Application No. 03 ($94,824.00), Trane Application No. 04 ($58,913.74), Parkhill invoices (two small line items), and two applications from A Brush Above Services, LLC including one for $1,066,854.45 relating to campus renovation. Outstanding finishes for the Elementary and High School were tabled by unanimous consent to the next regular meeting.