Board approves $25,000 engineering increase for Phase 1 after railroad delays

Village of Kincaid · October 27, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Chastain & Associates requested an additional $25,000 for Phase 1 engineering after a six-month railroad-related delay; Trustee Nelson moved to add funds and the board approved unanimously.

Mayor Pezze reported Chastain & Associates requested a $25,000 increase in their contract to cover added engineering labor costs related to a six-month delay caused by the railroad. CJ explained that placement of a water main in the railroad easement and the railroad's slow response delayed work and generated additional engineering effort.

Trustee Nelson moved to add $25,000 for engineering fees to Phase 1; Trustee Paso seconded and the motion passed with all ayes. The increased amount will be included in the Phase 1 loan. Trustees did not debate rescinding or renegotiating earlier contract terms at this meeting; they approved the requested increase to keep the project moving.