Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Solar Development topic

No spam. Unsubscribe anytime.

Marlborough fixes $227,412 performance bond for Highland 201 Solar stormwater work

Town Board, Town of Marlborough · May 27, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Town Board authorized a stormwater facility maintenance agreement and set performance security at $227,412 for the Highland 201 Solar project after Planning Board approvals and SEQRA review.

At the May 27 workshop, the Town Board adopted Resolution #62 authorizing the Town Supervisor to execute a Stormwater Control Facilities Maintenance Agreement with Highland 201 Solar and fixing the required performance security at $227,412. The resolution states the figure was provided by Highland 201 Solar’s engineer and approved by the Town Engineer as an estimate to complete the remaining stormwater facilities.

The resolution notes the Planning Board granted special permit and site plan approvals for the Highland 201 Solar project at properties on Milton Turnpike, and that completion of the facilities and delivery of performance security are conditions of those approvals. The board voted 4–0 to adopt the resolution, with Councilperson Molinelli absent.