Kenilworth beach opening delayed to July as contractors cite weather setbacks
Summary
A construction manager told the Village Board that weather-related delays have pushed the Beach Improvement Project completion date from early June to July 1, 2026. The village will consider phased opening options and staff will present alternatives to the board soon.
Get email alerts on the Beach Improvement Project topic
No spam. Unsubscribe anytime.
President Cecily Kaz asked Michael Cottick of Bulley & Andrews to brief the board on the Beach Improvement Project. Cottick said the project has encountered vendor challenges caused by inclement weather and that completion has moved from early June to an expected July 1, 2026. He told the board staff and the contractor are preparing alternative opening plans, including phased use of some beach facilities, to protect public safety while honoring residents’ interest in an opening.
"He highlighted that the challenges faced by construction vendors due to inclement weather have pushed the project’s completion date from early June to July 1, 2026," Cottick said during the presentation. President Kaz emphasized the need to balance community enthusiasm for the new beach facilities with safety for beachgoers and said the board and staff will aim to present options that allow some use if safe.
The board did not take action on the beach schedule; staff will return with draft opening plans and any operational or staffing implications once options are developed.