Street improvement schedule pushed back; draft relies on reserves and a paving needs assessment
Summary
Staff moved the South River Road neighborhood improvement project out of FY 26/27 to FY 27/28 and the draft shows use of prior reserves to help balance near‑term years; council budgeted a paving needs assessment and awaits local gas tax receipts before firming funding.
Get email alerts on the Streets topic
No spam. Unsubscribe anytime.
Council and staff reviewed changes in the Street Improvement Fund and discussed funding tradeoffs for near‑term capital projects.
Miss Vance (S5) told council the neighborhood improvements project (South River Road streetscape) was pushed from FY 26/27 to FY 27/28. Council members raised concerns about whether the draft reserve assumptions are realistic; the draft indicates the planned use of prior reserves in upcoming years to level expenditures, and staff said local option gas tax receipts and a planned paving needs assessment could alter those assumptions.
"Now we have budgeted, a paving needs assessment to determine if our non ad valorem is appropriate for our city streets and that those that we've annexed in," S4 said, noting analysis of assessment structure and potential alternative funding is underway. Council asked staff to quantify current reserve balances and to return with scenarios that show the impact of different gas tax receipts and reserve uses on the five‑year program.
No formal action was taken; staff will provide a reserves summary, paving assessment results and updated schedule scenarios for council consideration ahead of budget adoption.