Highway superintendent reports ditching, culvert work, paving and third-quarter water sampling
Summary
Highway Superintendent Jonathan Fish reported ditching and culvert installs, paving activity tied to Newcomb & Chestertown, museum-site work, hydrant painting and third-quarter water sampling. The board recorded the operational updates.
Get email alerts on the Public Works topic
No spam. Unsubscribe anytime.
Highway Superintendent Jonathan Fish reported several recent public-works activities: ditching work on Wamsley and Gouche roads with installation of three culverts and application of top coat; culvert and top coat on 14ths Road; three days of work at the museum including tar, drainage, topsoil and grass seed; paving and hauling activity tied to Newcomb and Chestertown with materials hauled from Saratoga; third-quarter water sampling; and routine hydrant painting, raking and brush cutting.
The superintendent’s update was presented as an operational report rather than an action item; no board vote was required. The minutes indicate ongoing maintenance work and scheduled tasks tied to seasonal road and water-system upkeep.