Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the Airport topic
No spam. Unsubscribe anytime.
Board hears $2.15 million engineering plan to rehabilitate Lansing airport runway
Summary
Crawford, Murphy & Tilly presented an engineering scope and a projected $2,150,000 budget for rehabilitation of Lansing Municipal Airport Runway 9/27, with federal and local match components. The proposal was placed on the Feb. 17 Village Board agenda.
Get email alerts on the Airport topic
No spam. Unsubscribe anytime.
D. Kyle Peabody, P.E., project engineer with Crawford, Murphy & Tilly, presented the proposed engineering services for rehabilitation of Runway 9/27 at Lansing Municipal Airport. Peabody outlined the scope of work: National Environmental Policy Act compliance, engineering report, preliminary and detailed design, contract construction plans and specifications, a construction safety and phasing plan with FAA coordination, estimates of probable project costs and duration, and assistance with bidder inquiries.
The minutes list a "Projected Budget $2,150,000.00" with a proposed funding breakdown: Federal Discretionary $1,442,500; Federal Entitlement $600,000; State match $53,750; Village match $53,750. Peabody gave a design/timeline window beginning July 1, 2025, through an anticipated construction start of May 1, 2027. "This will be placed on February 17, 2026, Village Board Meeting Agenda," the record states.
The committee did not take final action; the engineering agreement and funding strategy will be considered by the full Village Board on Feb. 17. If approved, the agreement would authorize design-phase services and associated FAA coordination ahead of construction.
