Summer maintenance schedules set for LaSalle and Parkview projects

Board of Education of Creve Coeur School District No. 76 · June 23, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Board heard updates on multiple summer projects: boiler pump installation at LaSalle (to be completed before Aug. 3), Parkview re-roof scheduled July 23–28, LaSalle door replacement July 6–17, heat detector installation completed June 23, and parking lot sealing projected to begin July 6.

Superintendent Johnson reported the status and schedules for several summer maintenance projects. DMI plans to finish installing new pumps in the LaSalle boiler room before Aug. 3; the Parkview re-roof is scheduled for July 23–28 (weather permitting); door replacement at LaSalle is scheduled to begin July 6 with anticipated completion July 17. Johnson Controls completed the heat detector installation at LaSalle Elementary on June 23, and sealing and striping of the LaSalle parking lot is projected to begin July 6.

These projects are part of the district's routine summer maintenance program; the Board received the updates and did not record additional motions linked to the project schedules in open session.