County approves $11,297.92 change order for jail HVAC to support energy recovery ventilators
Summary
The board approved Change Order 003 for the Black Hawk County Jail HVAC and building automation upgrade, adding $11,297.92 for direct digital control work required for Energy Recovery Ventilators, as recommended by Facilities Director Rory Geving.
Get email alerts on the Facilities topic
No spam. Unsubscribe anytime.
The Black Hawk County Board of Supervisors on Aug. 4 approved Change Order 003 for the county jail HVAC and Building Automation System upgrade, adding $11,297.92 for additional direct digital control work required to operate Energy Recovery Ventilators. Facilities Director Rory Geving recommended acceptance and the chair was directed to sign the change order.
Supervisor Justin Brandt moved the resolution, seconded by Tavis Hall; the board recorded unanimous approval. The change order covers specific control work needed for the Energy Recovery Ventilators and is part of the broader jail HVAC upgrade project overseen by county facilities staff.