Superintendent reports Phase III HVAC work mostly complete; project cost just over $4.6M
Summary
Superintendent J. Henry told the board the Phase III HVAC work concluded Aug. 1, 2025, with minor punch-list items remaining and two rooftop units requiring a manufacturer's visit; the three-year project totaled just over $4.6 million, Henry said.
Get email alerts on the Facilities topic
No spam. Unsubscribe anytime.
Superintendent J. Henry reported at the Aug. 11 meeting that Heartland Mechanical Contractors completed the major portion of the district's Phase III HVAC project on Aug. 1, 2025, though a handful of punch-list items remain.
Henry said two rooftop units had minor problems when first started and that a Daikin representative was scheduled to complete those repairs. "In total, the 3-year project totaled just over $4.6M and impacted almost every area of the building," the superintendent told the board, adding that the district will schedule detailed central-controls training and then permit limited in-room decentralization within established parameters.
The board did not receive dollar-by-dollar line-item detail during open session. Henry praised custodial and maintenance staff and summer student workers for their role getting the building ready for the start of school.