Summary
Officials reported an EPA inspection at the future Well #10 site and said a land survey and an easement with Harvest Baptist Church (signed April 16, 2025) are required before construction; Choice One Engineering supplied the legal description and Village Law Director Jeff Forbes drafted Ordinance #2025-010.
Get email alerts on the Water Supply topic
No spam. Unsubscribe anytime.
Village officials reported that the EPA has conducted an inspection of the future site for Well #10 and identified pre-construction requirements. Committee members recorded that a land survey and an easement agreement with Harvest Baptist Church — including a legal description to be recorded with the county — must be in place before final construction can begin.
Choice One Engineering provided the required legal description, and Village Law Director Jeff Forbes drafted Ordinance #2025-010 for council approval. The meeting record notes that Steve Jackson, owner of Harvest Baptist Church, met with Village staff on April 16, 2025, and signed the easement forms.