ODOT to cover over-budget paving costs on Route 42 project; Barrett Paving was low bidder
Summary
ODOT District 8 will cover a 7% budget overrun on the Route 42 and North Street paving project after Barrett Paving submitted the lowest bid; the Village reported receiving $128,000 in County Vehicle Tax funds to cover its $250 contribution.
Get email alerts on the Paving Route42 topic
No spam. Unsubscribe anytime.
Village Manager Gary Copeland told council that ODOT put the Route 42 and North Street paving project out to bid. Barrett Paving submitted the lowest bid but the bid was 7% higher than the Village’s budgeted amount; ODOT District 8's Safety Program will cover the increased paving cost.
Copeland also reported the Village has received $128,000 from County Vehicle Tax funds that, in part, cover the Village’s contribution (noted as $250 in the minutes) to the project. No contract award was ratified during the March 17 meeting; council received the update as part of the Village Manager’s report.