Engineers give timeline for OSLAD park work, aim to open parking by May 1

Village of Sheffield Village Board · February 10, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Chamlin Engineering told the Village of Sheffield board that Contract 1 of the OSLAD-funded park work aims to finish a parking area by May 1, 2026 for summer baseball; Contract 2 bids open Feb. 27 for concession, shelter and lighting with fall 2026 completion expected.

Chamlin Engineering representatives Tim Harris and Josh Washkowiak updated the Village of Sheffield board on the status of the OSLAD-funded park project, saying Contract 1 targets completion of the parking area by May 1, 2026 to accommodate summer baseball.

Harris and Washkowiak told trustees that Contract 2 is currently out for bid with a bid opening scheduled for Feb. 27, 2026; that phase includes construction of the concession stand, a shelter and installation of lighting, with anticipated completion in Fall 2026. Contract 3 will address specific equipment purchases at a later date.