Planning board approves final subdivision and related permits for Elmwood Preserve after extended environmental review

Greenburgh Planning Board · August 5, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

After an eight‑year review and coordination with NYSDEC brownfield cleanup requirements, the board approved a final subdivision, amended steep slope and wetland permits, and a tree removal permit for the Elmwood Preserve project, subject to a lengthy list of construction and remediation conditions.

The Planning Board voted to waive a public hearing and approved multiple final decisions for the Elmwood Preserve project at 850 Docks Ferry Road, concluding an eight‑year review that included an environmental impact statement and supplemental findings tied to New York State DEC brownfield cleanup actions.

David Steinmetz, counsel for the applicant, described the forty‑page final resolution as the implementation pathway for construction sequencing, remediation, stormwater controls and steep‑slope protections drafted by town staff and consultants. Owner Jonathan Gribo outlined the remediation sequencing and monitoring by the DEC, estimating the cleanup as “north of a $10,000,000 cleanup operation on this property” and acknowledging the figure could be “closer to $20,000,000” to achieve full remediation.

Gribo and project engineer Diego Villareal explained remediation and phasing: the remediation will proceed quadrant by quadrant with testing at multiple depths, stockpiling of contaminated material, daily logs and reporting, and a staged approach to infrastructure followed by homebuilding. Gribo estimated remediation at roughly 9–15 months depending on DEC review pace and suggested a 1‑year cleanup, followed by about a year of infrastructure work and three to four years for home construction — a total phasing horizon he estimated at five to six years in current market conditions.

Town staff and outside consultants confirmed that updated conditions reflect expanded remediation limits, revised disturbance figures, enhanced perimeter landscaping, sediment/erosion controls and a monthly escrow to fund an on‑site independent monitor selected by the town to oversee remediation and environmental operations.

The board voted on five items: to waive the public hearing on final subdivision, approve the final subdivision decision, approve the amended steep slope permit, approve the amended wetland/watercourse permit, and approve the tree removal permit; all motions carried by voice vote. The approvals include detailed construction conditions and tracking requirements that tie continued home development to completion of DEC‑required cleanup and associated monitoring.

What comes next: the applicant must comply with the conditions, post escrow funding for on‑site monitoring, and continue DEC coordination. Staff will finalize the approval letters and monitor condition compliance through the town’s review processes.