Board approves Eden Elementary roof change orders, flags $223,365 of additional wet insulation
Summary
The Eden Central School District board approved capital project change orders for Eden Elementary roof work that include $223,365 for additional wet insulation replacement; the superintendent said the district is pursuing insurer reimbursement but has voter-approved project funds available if needed.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
The Eden Central School District Board of Education approved capital project change orders related to the Eden Elementary roof replacement, including $223,365 for additional replacement of wet insulation.
"This is all of this work... is for the Eden Elementary roof," the superintendent said while noting the larger wet-insulation bill and that the district is working with its insurance carrier to determine coverage. The board voted to approve the change orders by voice vote after a second.
The motion included smaller line items such as curb access panels ($4,078) and metal coping replacement ($2,492). The superintendent said that even if the insurance carrier does not cover the additional work, funds are available from the voter-approved capital project to complete the necessary repairs.
The board also discussed increased oversight on change orders and a revised corrective action plan in response to an Office of the State Comptroller audit; the corrective action plan was approved later in the meeting and is to be resubmitted to the comptroller's office.