Summary

The board heard that demolition of the district's tennis courts has begun, the top asphalt will be milled and a third‑party sub‑base inspection is planned; after new asphalt is placed a 14–30 day curing period will be required and signs will direct the public to alternate courts.

District staff reported demolition of the tennis courts is underway and that the contractor will mill the top asphalt layer and arrange a third‑party inspection of the sub‑base before new surfacing.

According to the update, "After the new asphalt is laid, it will require a 14 to 30-day curing period before further work can be done." The district documented the condition of the existing courts and offered the previous contractor's legal counsel an opportunity to test the site; that counsel opted to take photographs only. The district will post signage to direct community members to alternative courts during construction.

The board did not take formal action on the courts during the special session; staff will continue to oversee inspection and remediation steps as needed.