Hilton driveway and roundabout work on schedule; board told power shutdown planned June 19

Brecksville-Broadview Heights Board of Education · June 1, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

District construction update said Hilton driveway and roundabout are progressing, light pole bases are being installed, and an electrical panel replacement at the board office will require a brief power shutdown on June 19; the district is handling a change order and sediment runoff affecting Chippewa Hills HOA.

Superintendent Jeff Harrison introduced Brian Koss to brief the board on current campus construction on June 1.

Koss reported the Hilton driveway project is progressing on schedule: "The project is progressing well and is currently on schedule, with about two months remaining." He said light pole bases are being installed and that an electrical panel at the board office needs full replacement, requiring a brief power shutdown scheduled for June 19. Koss also described a change order for the 'Y' curve near the stadium and said the district is addressing sediment runoff issues affecting the neighboring Chippewa Hills HOA; excess dirt is being trucked off site because of space limitations.

Board members heard that Phases 1 and 2 of the campus master plan are funded and underway while later phases remain conceptual and unfunded. The construction update did not include a final completion date for subsequent phases.