River Ridge board ratifies $150,786.09 change order after member urges review of budgeting process

River Ridge Community Development District · January 28, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The River Ridge Community Development District ratified a $150,786.09 change order for Phase I/II stormwater projects after debate about carryover funds and project timing; the board directed counsel to draft ground rules for future over-budget field decisions.

The River Ridge Community Development District Board ratified MRI Construction Change Order Estimate #500 for price changes to Phase I and Phase II stormwater management projects, in the amount of $150,786.09, on a unanimous vote. The motion was made by Supervisor Kurt Blumenthal and seconded by Supervisor Keith Merrill; the minutes record the motion passing "with all in favor."

Supervisor Terry Mountford criticized the approval process, saying "there is a major dysfunction in the CDD’s operating process" and noting the CDD was "already $300,000+ over budget" before the additional expenditure. District Engineer Charlie Krebs and Supervisor Blumenthal countered that the expenditures stemmed from project timing and funds carried over into Fiscal Year 2025, and that the change produced a functioning solution to eliminate standing water. The board directed District Counsel Tony Pires to draft "ground rules" for approving field change orders above a specified amount and to consider requiring special meetings or defined contingency authority for project managers.