Board approves $3,098 'zombie box' instead of immediate aerator relocation (3–2)
Summary
Faced with a $10,755 proposal to relocate a lake aeration system in Lake E1‑C, the River Ridge board voted 3–2 to install a $3,098 'zombie box' at the existing location and defer relocation costs for further budget discussion. Mountford and Blumenthal dissented.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
District operations staff presented Premier Lakes’ work order and a revised electrical proposal from Bentley Electric to relocate an aeration system in Lake E1‑C. The revised electrical work would add about 125 feet and increase cost; staff and board members discussed budgeting the relocation in Fiscal Year 2026 and alternative, lower-cost interim solutions.
After discussion, the Board approved installing a "zombie box" at the existing aeration location for $3,098 and to revisit the $10,755 relocation proposals during proposed FY2026 budget discussions. The minutes record the motion and result: "On MOTION by Mr. Schultz and seconded by Mr. Twombly, with Mr. Schultz, Mr. Twombly and Mr. Merrill in favor and Mr. Mountford and Mr. Blumenthal dissenting, installing a zombie box, in the amount of $3,098, was approved. [Motion passed 3-2]" The vote was recorded 3–2 in the minutes.
The decision defers higher relocation costs while authorizing a lower-cost interim measure; the minutes do not record public comment on this item.