Water-treatment plant overhaul proposed; staff recommends 15% rate increase for 2026

Aspen City Council · October 13, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Utility staff told council the water-treatment plant needs filter replacements, consolidated chemical systems and improved residuals handling; staff budgeted $15 million in 2026 for long-lead purchases and proposed a 15% water-rate increase in 2026 as part of the financing plan.

Deputy Utilities Director Ryan Labock and colleagues described the water-treatment plant project as driven by aging filters (some more than 40 years old), operator-safety concerns and anticipated state discharge requirements for backwash water. Labock said the project will consolidate chemical dosing and add engineered solids-handling infrastructure to meet stricter regulations.

Labock told the council staff has budgeted $15,000,000 for 2026 to purchase long-lead equipment and to fund early construction-yard setup, trailers and initial site work. On financing, staff said council had directed pursuit of option 2 in which a proposed 15% water-rate increase in 2026 would help fund the project; staff also cautioned that flattening out future rate increases could jeopardize maintaining a 25% fund balance for the utility.

Council members asked about customer impacts and the timing of GMP and bidding; staff said Haskell was selected as the construction manager at risk and that the early procurement of long-lead items is intended to let work start in October while preserving competition for the larger packages.