Council approves wastewater plant chemical-addition bid, multiple construction estimates and a retaining-wall emergency declaration

City of Alma Common Council · April 16, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Council approved a $79,446 construction bid for a chemical addition building at the wastewater treatment plant, authorized up to $7,000 for materials, approved concrete, fence and landscaping estimates, and adopted an emergency declaration for Phase 2 of the 2nd Street retaining wall.

The council approved multiple public-works actions related to the wastewater treatment plant and street infrastructure on April 16.

The Utilities Committee reported receiving a bid from R.J. Jurowski Construction, Inc. of Whitehall, Wisconsin, for $79,446.00 to construct a chemical addition at the wastewater treatment plant. The transcript records: "Motion by Earney seconded by Brommer to approve the R.J. Jurowski Construction bid for $79.446.00. Earney voting no and Meier, Grisen, Brommer, Iberg, Mueller, and Jepsen voting yes by roll call vote." The council also authorized Foreman Wick to spend up to $7,000 on materials for the chemical-addition building and approved contractor estimates for concrete (Turnbell Masonry, $145,000), a chain-link fence (Cyrus Landscaping, $65,400), and landscaping ($56,202).

Separately, the Mayor presented an emergency declaration for Phase 2 of the 2nd Street retaining wall and the council approved the declaration by roll call. Councilors also approved a motion to investigate reallocating the fire protection charge from the general fund to sewer/water utility billing.