HPISD receives bond update on MIS-HPMS chilled-water piping replacement
Summary
Assistant Superintendent Scott Drillette told trustees the district completed replacement of the MIS-HPMS chilled water piping system over the summer and outlined remaining bond-funded work to finish the project.
Get email alerts on the Bond topic
No spam. Unsubscribe anytime.
The Highland Park Independent School District Board of Trustees heard a bond-program update from Scott Drillette, Assistant Superintendent for Business Services, about summer work to replace the MIS-HPMS chilled water piping system and remaining tasks tied to the project. Drillette reported the piping replacement was completed over the summer and highlighted additional work that still needs to be finished as part of the bond program.
The presentation focused on project status and next steps; no formal board action or vote was taken on the item during the work session. Trustees present included President Maryjane Bonfield and Vice President Bryce Benson. The district did not specify final cost or a completion date in the minutes; those details were not specified.