Kemp ISD selects CMAR delivery method for proposed animal barn with $1.8M cap

Board of Trustees, Kemp Independent School District · November 18, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Board members adopted a resolution selecting Construction Manager at Risk (CMAR) for the animal barn and limited initial authorization to $1.8 million; any additional funding would require returning to the board for approval.

Kemp ISD trustees voted Nov. 18 to adopt a resolution selecting Construction Manager at Risk (CMAR) as the delivery method for construction of an animal barn on district property, with a limit that initial authorization shall not exceed $1.8 million without returning to the board for further review and approval.

Trustee Matt Gross moved to adopt the resolution; Trustee Randal Robertson seconded and the motion passed unanimously. The minutes record the board's agreement that CMAR is the preferred delivery method "with one exception not to exceed 1.8 million." If additional funds are required, the matter will return to the board.

The resolution sets the procurement approach and an initial fiscal cap for the project; the transcript does not include a project schedule, contractor selection, or final total project estimate.