Salt dome nearing completion; committee approves $97,000 estimated line-power transition at Richards Pit
Summary
Salt dome walls and roof are complete with expected early-September finish for paving and doors; reliability issues at the Richards Pit prompted approval to transition to line power at an estimated cost of $97,000 (motion carried).
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
Brian Trebiatowski reported that the salt dome replacement walls and roof are complete; backfilling and paving are scheduled prior to overhead-door installation and final punch-list work, and he estimated the project would reach completion in early September.
Separately, Trebiatowski reported generator reliability problems at the Richards Pit during production and recommended transitioning to line power. He outlined cost components: Adams Columbia costs of just over $57,000 to bring power to the lower floor, plus approximately $30,000–$40,000 for a control cabinet, transformer, wiring and electrician labor. The committee approved the transition to line power for an estimated total cost of $97,000 (motion moved by John Bennett, seconded by Dave Benson).