Superintendent reports concrete work, 95-day weather delays and higher-than-expected roofing estimates
Summary
Superintendent Parton told the MUNDAY CISD trustees on Nov. 21 that concrete was poured and concession-stand work continues; weather delays have totaled 95 days and a roofing estimate from Booe came in about three times the insurance estimate, prompting staff to seek additional bids and deed review.
Get email alerts on the Facilities topic
No spam. Unsubscribe anytime.
Superintendent Mr. Parton updated the Board of Trustees on construction activity at district facilities during the Nov. 21 meeting, saying concrete was poured that day and work was underway on the concession stand.
Parton said weather delays have amounted to 95 days and warned that any additional delay could result in liquidation costs. He reported that a roofing estimate from Booe was roughly three times what insurance had projected and that HPA provided a lower estimate. To help contractors prepare accurate bids, Parton said the district has engaged a consultant to gather deeds. He also noted the district's School Board Training is scheduled for Dec. 14, 2024.