Board ratifies parking-lot GMP, approves change order and final payment for PHS lot
Summary
The Board ratified a GMP amendment for the PHS parking lot (final cost $849,454.94), approved Change Order No. 1-A-001 for additions, and accepted the work and final payment.
Get email alerts on the Construction Parking topic
No spam. Unsubscribe anytime.
Finance Manager Angel Grant told the Board that the PHS parking lot GMP was originally $718,264.00 and that change orders for a band director tower, added power to a new PHS scoreboard, relocation of an existing scoreboard to Pampa Junior High and stadium light pole line repairs increased the final cost to $849,454.94; the work is complete.
Trustees approved and ratified GMP Amendment No. 1‑A, approved Change Order No. 1‑A‑001, and accepted the work and final payment for Subproject No. 1‑A; motions were made and carried unanimously. The superintendent was authorized to execute the final completion certificate and take necessary actions for final payment and acceptance.